SABAH AL AHMAD MEW 132/11KV Substations Project is another turn key project we are handling right now.
The project consists of 8 nos. 132/11 kV substations namely Sabah Al Ahmad 2A,4A,2B,4B,4D,2G,2H and 2K
The substation building is fully equipped with a state of the art Fire Alarm System supplied from SIEMENS.
The transformer yards are protected by Water Spray System from Viking.
Fire Alarm System consists of 16 Fire Alarm & Extinguishing Control Panels and around 1500 Field Devices installed.
Water Spray System Consists of 32 nos. 4” Deluge Valves, 1400 Spray Nozzles, 8 Pressure Tanks, 16 Jockey Pumps & 16 Air Compressors